Sr. No. |
Particulars |
Unit |
Details |
1 |
Length
|
Km
|
30.128
|
15.546
|
2 |
Row
|
|
|
|
Existing ROW (M)
|
|
|
|
|
Km. 0/000 to 18/648
|
Mt
|
15
|
|
|
Km. 18/648 to 30/128
|
Mt
|
12
|
|
|
Km. 0/000 to 26/460
|
Mt
|
|
14
|
|
Proposed ROW (M)
|
|
|
|
|
Km. 0/000 to 18/648
|
Mt
|
15
|
|
|
Km. 18/648 to 30/128
|
Mt
|
12
|
|
|
Km. 0/000 to 26/460
|
Mt
|
|
14
|
3.1 |
Pavement Type Section-A
|
|
Intermediate Lane (Km)
|
Two Lane with Paved Shoulder (Km)
|
|
Reconstruction
|
|
|
3.500
|
|
Widening
|
|
|
23.300
|
|
Overlay Section
|
|
|
|
|
Rigid Pavement
|
|
|
3.328
|
Total Length (KM)
|
30.128
|
3.2 |
Pavement Type Section-A
|
|
Intermediate Lane (Km)
|
Two Lane (Km)
|
|
Reconstruction
|
|
|
|
|
Widening
|
|
14.346
|
|
|
Overlay Section
|
|
|
|
|
Rigid Pavement
|
|
1.200 |
|
Total Length (KM)
|
15.546
|
5 |
Major Bridges
|
|
|
|
5.1 |
New Construction / Re-Construction
|
NOS
|
1
|
0
|
|
Minor Bridges
|
|
|
|
5.1 |
New Construction / Re-Construction
|
NOS
|
3
|
4
|
6 |
Slab Culvert
|
|
|
|
6.1 |
New Construction / Re-Construction
|
|
2
|
1
|
6.2 |
Widening
|
|
0
|
0
|
8 |
Pipe culverts
|
|
|
|
8.1 |
New Construction/ Reconstruction
|
|
41
|
35
|
8.3 |
Widening
|
|
34
|
16
|
8.4 |
Retained
|
|
0
|
0
|
9 |
Junctions Improvement
|
|
|
|
9.1 |
Major junctions
|
|
3
|
3
|
9.2 |
Minor Junction
|
|
17
|
8
|
10 |
Bus Shelter
|
NOS
|
4
|
6
|
11 |
Covered RCC drain
|
Rmt
|
6656
|
2400
|
12 |
Retaining wall
|
Rmt
|
2200
|
300
|