Improvement to Mokhada-Kasara-Dolkhamb-Tokawade-vaishakhare-Mhasa Road SH 78 Km.44/000 to 130/540 Tal.Shahapur & Murbad Dist. Thane hybrid Annuity Basis Package No.MU-5

Item Stage for measurement for physical progress Unit Qty Weightage in percentage to the Contract Amount as Tender (In Cr.) Physical Work Physical Progress in % Financial Progress (Amount) Financial Progress in % Remarks
Road works including culverts, minor bridges, underpasses, overpasses, approaches to ROB/RUB/ Major Bridges/ Structures (but excluding service roads) A – Widening and strengthening of existing road
(1) – Earthwork upto the Subgarde Km. 80.35 4.53 6.31 23.50 1.32 1.84 1.32
(2) – Granular Work Subbase,base Shoulder) Km.
(a). GSB Km. 80.35 20.02 27.87 23.07 5.75 8.00 5.75
(b). WMM Km. 80.35 13.15 18.31 9.09 1.49 2.07 1.49
(3). Shoulders Km. 80.35 0.90 1.25
(4). Bituminous work Km.
(a). BM Km. 78.79 1.79 2.49
(b). DBM Km. 78.79 15.76 21.94
(c). BC Km. 78.79 8.27 11.51
(5). Rigid Pavement Km.
Concrete work Km. 1.56 5.33 7.42
(C). – New culverts, minor bridges,underpasses, overpasses
(1). Culverts Nos. 240.00 6.41 8.92 48.00 1.28 1.78 1.28
(2). Minor bridges Nos. 12.00
(a). Foundation Nos. 39.00 0.64 0.89 7.00 0.11 0.16 0.11
(b). Sub-structure Nos. 39.00 3.45 4.80 3.00 0.27 0.37 0.27
(c). Super-structure (including crash barriers etc. Nos. 27.00 1.75 2.44 2.00 0.13 0.18 0.13
(3). Cattle/Pedestrian underpasses/Slab Nos. 9.00
(a). Foundation Nos. 18.00 0.19 0.26 2.00 0.02 0.03 0.02
(b). Sub-structure Nos 18.00 1.27 1.77
(c). Super-structure (including crash barriers etc. Nos 9.00 0.80 1.11
Major Bridge works and ROB/RUB A – Widening and repairs of Major Bridges Nos. Nos. 1.00
(2). Sub-structure Nos. 9.00 0.19 0.26
(3). Super-structure (including Nos 10.00 0.06 0.08
C – New Major Bridges Nos.
(1). Foundation Nos 1.00
(a). Open Foundation Nos. 6.00 0.20 0.28
(b). Pile Foundation/Well Foundation Nos.
(2). Sub-structure Nos 6.00 0.70 0.97
(3). Super-structure (including crash barriers etc. complete) Nos. 5.00 0.46 0.64
(iv) Road signs, markings, km stones, safety devices,.
(a). Road signs, markings,km stones Km. 80.35 1.41 1.96
(b). Concrete Crash Barrier/ WBeam Crash Barrier in Road work Km. 11.06 4.41 6.14
(v) Project facilities
(a) Bus bays Nos 26.00 1.20 1.67
(vii) Road side plantation Km. 80.35 0.39 0.54
(b) Toe/Retaining wall Km 2.82 5.38 7.49
(x) Miscellaneous (Site clearance, Quality Control,Crust removal/ scarifying, Tree cutting, Arboriculture etc.) Lump Sum 1.00 1.34 1.87 0.23 0.31 0.43 0.31
Total 100.00 139.22 10.68 14.87 10.68